Early delivery from QTS of commissioned space in new hyperscale data center​

18 Aug 2018

10 months since it commenced, the first phase development of the QTS Realty Trust 32 megawatt facility has been completed.

QTS says the early delivery of commissioned space in its new Ashburn, Virginia, mega data center is a direct response to increased demand for hyperscale data center and hybrid colocation solutions.

The company only broke ground on the undeveloped land during the third quarter of last year, attributing its ability for the rapid delivery of a full powered shell and four megawatts of initial turn-key capacity to an innovative modular design, in addition to scalable mechanical and electrical systems.

The facility also benefits from acres of adjacent land already designated for future expansion.

In terms of the actual data center, when its finished it will hold the mantle (for how long, who knows) for the first and only three-story data center in Ashburn. Approximately 180,000 square feet of data center space spread over 12 column free data halls will benefit from up to 32 megawatts of critical power capacity that QTS asserts has been optimized for enterprise, hyperscale, and build-to-suit solutions.

Furthermore, the data center will host a 50,000 square foot office complex that will serve as the new campus for QTS’ Hyperscale, Federal, and Northern Virginia-based teams.

"QTS has aligned our development strategy to rapidly deliver high quality data center solutions that meet customers' requirements for location, speed, scale and economics," says QTS chief hyperscale officer Tag Greason.

"Northern Virginia is the nexus for connectivity, and we look forward to providing critical capacity for large organizations with hyperscale consumption requirements and hybrid colocation needs."

QTS asserts the new facility represents the next phase of its growth strategy with the company’s existing facility in Northern Virginia in addition to the vacant adjacent land, the company has the capability to deliver aggregate data center capacity exceeding 225 megawatts to the Northern Virginia market.

Story image
CSPs need to shift their 5G strategy if they want to keep up
“Fundamentally, CSPs must become 5G ecosystem orchestrators. That's the only way they can hope to meet enterprise business needs and re-integrate themselves into enterprise 5G value-chain as the world emerges from the COVID-19 pandemic.”More
Story image
HPE rolls out GreenLake Central, delivering edge to cloud solution
First unveiled in December last year, the service aims to bring the cloud experience to customers’ applications in a self-serve, pay-per-use, scale up-and-down way and managed as-a-Service by HPE.More
Story image
Operators must secure spectrum to revive 5G rollouts in 2020 - report
New research from a recently released report from GlobalData suggests that the delay of spectrum allocations and auctions due to health and financial concerns is more directly linked to the slowdown in operators’ rollout plans than previously thought.More
Story image
GoDaddy reveals widespread data breach
The company, which is the world’s biggest domain registrar with 77 million domains and 19 million accounts, apologised to an undisclosed number of its users in an email.More
Story image
Amazon commits to five new utility-scale solar projects
The projects in China, Australia, and the U.S. will total 615 MWh. Comes as Amazon criticised for conditions and lack of paid sick leave in U.S.More
Story image
Dell and Google Cloud deepen integration to bolster hybrid cloud storage
Dell and Google Cloud have announced the launch of their new hybrid cloud storage system, with the capability of moving as much as 50 petabytes of high-performance workloads.More